1.10/11/2008 10:50am
Areas of damaged concrete have been marked out for patch repairs
-
2.10/11/2008 14:26
Breaking out manhole lids for lifting to proposed level
-
3. 11/11/2008 09:02
Breaking out existing damaged areas
-
4. 11/11/2008 10:58
Patches planed out using a 500mm planer and sweeper
-
5. 11/11/2008 12:59
Tie ins planed out and planed areas tack coated
-
6. 11/11/2008 14:35
HDM patches laid and compacted
-
7. 12/11/2008 09:36
Zone 1 tack coated and Regulating layer being laid
-
8. 12/11/2008 12:13
Regulating being finished and GlasGrid reinforcement installed
-
9. 12/11/2008 16:24
Majority of GlasGrid installed and Manholes being raised
-
10.13/11/2008 08:49
Open Graded Asphalt (OGA) being laid
-
11. 13/11/2008 13:57
OGA completed
-
12. 14/11/2008 13:02
Grouting of OGA (mixing)
-
13. 14/11/2008 13:24
Grouting of OGA (installation)
-
14. 14/11/2008 16:00
Area Grouted in Day first day
-
15. 17/11/2008 09:27
QA testing to ensure correct workability of grout
-
16. 17/11/2008 12:41
Area of grouting completed in day 2 (markings on 15&16/11/2008)
-
17. 18/11/2008 16:39
Markings completed and ready for loading
-
18. 19/11/2008 7:30
Reloading of area started on evening of 18/11/2008